Project update: May 2026

1 May 2026

All eight speed humps are now completed and line marked. There are two locations remaining where signage is to be installed. A small portion of asphalt works are to be completed mid to late May, these include the remaining works on the widening sections, the wings on all speed humps and the red asphalt slow point on Gabler Road.