Project Update: March 2026

4 March 2026

Beale Park changerooms reach lock-up

The facility has now reached lock-up, with the roof, brickwork and plumbing in place and the structure able to be securely locked.

The essential services that will power and run the facility are now installed, including:

  • Electrical wiring
  • Plumbing
  • Heating, cooling and ventilation systems
  • Roof sealing to ensure the building is weather-tight

What’s happening now

Construction is moving further into the internal fit-out stage. Current works include:

  • Installing internal wall linings
  • Fitting door frames
  • Preparing wet areas ahead of tiling

What’s next

Next month, the team is scheduled to:

  • Install metal exterior cladding
  • Install 17 tower lights
  • Install ceiling framing
  • Fit aluminium window frames and glazing
  • Complete waterproofing in the changerooms before tiling begins
  • Install the site’s main switchboard

The building is expected to be completed by the end of May.

The broader Beale Park redevelopment – including seven pitches, upgraded carparking and a new playground – is scheduled for completion in early 2027.