Project update: August 2024

13 August 2024

Playground coming early 2025

Considering community feedback, Council approved the budget for this playground at their Special Council Meeting in June 2024.

Playground Delivery

The procurement process is now underway, and construction is anticipated to begin in early 2025, subject to contractor availability. The project is expected to take approximately three months to complete, depending on site and weather conditions.

Works may include light concreting and earthworks. While the playground area will be fenced off during the construction period, we expect minimal disruption to the rest of Waterbuttons Park. The City will contact neighbouring residents closer to the time to advise them of the works.

More information

Consultation for this project has now concluded.