Jandakot Road - March to November 2019

Share Jandakot Road - March to November 2019 on Facebook Share Jandakot Road - March to November 2019 on Twitter Share Jandakot Road - March to November 2019 on Linkedin Email Jandakot Road - March to November 2019 link

Consultation has concluded


Georgiou Group has been appointed to deliver the upgrade of Solomon Road and Jandakot Road in Treeby, from 5 March to November 2019.

Timeframes are subject to change and depend on weather conditions. Electronic signboards will advise key information. On various nights, traffic management with lane closures will be in place while contractors relocate signs, install barriers and line marking, and remove the existing road medians.

Please drive carefully and adhere to the speed limit and directional signs. Nearby residents may experience construction-related noise and vibration. Every effort will be made to minimise disruption to the local community. Thank you for your patience while we complete these vital works. If you have any questions, please contact Georgiou Project Manager Toby Taylor on 0437 805 163.

In related news, the final drawings for the next stage of Jandakot Road upgrade, due to be delivered in 2020 are shown here. A copy of drawings can be reviewed on request at the Admin Centre in Spearwood on request. Please email [email protected].


Milestones

Preliminary work includes:

  • Relocate existing fencing late March 2019
  • Clearing, topsoil, cut to fill, cut to spoil, late March
  • Install Water Corporation main water bore April 2019
  • Relocate gas main April 2019
  • Drainage works May 2019
  • Western Power relocation works April - July 2019

Dollier Street

  • Drainage and roadworks April - May 2019

East of Solomon Road:

  • Road preparation and kerbing May - June 2019
  • Footpaths May 2019
  • Asphalt June 2019

West of Solomon Road:

  • Asphalt July 2019
  • Road preparation and kerbing July 2019

Pepperworth Place

  • Draining and roadworks July 2019

Solomon Road

  • Reinstatement of pavement July - August 2019
  • Install new fencing and gates July 2019
  • Solomon Road South works September 2019

Jandakot Road

  • Remove existing fencing late March 2019
  • Excavate trenches and install underground cables (Western Power) April - May 2019

South of Jandakot Road:

  • Clearing, drainage works and March - April 2019
  • Road base preparation and kerbing May - June 2019
  • Footpaths and asphalt July 2019

Reinstatement of existing Jandakot Road

  • Drainage works April 2019
  • Construct temporary pavement May 2019
  • Seal road July 2019
  • Footpaths July 2019
  • Asphalt July 2019

Tie in point works to existing Jandakot Road west side

  • Drainage
  • Road preparation and kerbing
  • Asphalt

Tie in point works to existing Jandakot Road east side

  • Drainage, road preparation and kerbing September 2019

Fraser Road

  • Earthworks, Drainage, Roadworks April - May 2019

Cessna Drive

  • Drainage, road preparation, kerbing asphalt July - August 2019

Coonadoo Court

  • Drainage, road preparation, kerbing, asphalt July - August 2019

Deliveries to Site

  • Late April 2019 – October 2019

Final works

  • Barriers, new fencing and gates, street lighting, signage and linemarking September 2019
  • Landscaping and verge reinstatement October/November 2019

Completion

  • November 2019


Georgiou Group has been appointed to deliver the upgrade of Solomon Road and Jandakot Road in Treeby, from 5 March to November 2019.

Timeframes are subject to change and depend on weather conditions. Electronic signboards will advise key information. On various nights, traffic management with lane closures will be in place while contractors relocate signs, install barriers and line marking, and remove the existing road medians.

Please drive carefully and adhere to the speed limit and directional signs. Nearby residents may experience construction-related noise and vibration. Every effort will be made to minimise disruption to the local community. Thank you for your patience while we complete these vital works. If you have any questions, please contact Georgiou Project Manager Toby Taylor on 0437 805 163.

In related news, the final drawings for the next stage of Jandakot Road upgrade, due to be delivered in 2020 are shown here. A copy of drawings can be reviewed on request at the Admin Centre in Spearwood on request. Please email [email protected].


Milestones

Preliminary work includes:

  • Relocate existing fencing late March 2019
  • Clearing, topsoil, cut to fill, cut to spoil, late March
  • Install Water Corporation main water bore April 2019
  • Relocate gas main April 2019
  • Drainage works May 2019
  • Western Power relocation works April - July 2019

Dollier Street

  • Drainage and roadworks April - May 2019

East of Solomon Road:

  • Road preparation and kerbing May - June 2019
  • Footpaths May 2019
  • Asphalt June 2019

West of Solomon Road:

  • Asphalt July 2019
  • Road preparation and kerbing July 2019

Pepperworth Place

  • Draining and roadworks July 2019

Solomon Road

  • Reinstatement of pavement July - August 2019
  • Install new fencing and gates July 2019
  • Solomon Road South works September 2019

Jandakot Road

  • Remove existing fencing late March 2019
  • Excavate trenches and install underground cables (Western Power) April - May 2019

South of Jandakot Road:

  • Clearing, drainage works and March - April 2019
  • Road base preparation and kerbing May - June 2019
  • Footpaths and asphalt July 2019

Reinstatement of existing Jandakot Road

  • Drainage works April 2019
  • Construct temporary pavement May 2019
  • Seal road July 2019
  • Footpaths July 2019
  • Asphalt July 2019

Tie in point works to existing Jandakot Road west side

  • Drainage
  • Road preparation and kerbing
  • Asphalt

Tie in point works to existing Jandakot Road east side

  • Drainage, road preparation and kerbing September 2019

Fraser Road

  • Earthworks, Drainage, Roadworks April - May 2019

Cessna Drive

  • Drainage, road preparation, kerbing asphalt July - August 2019

Coonadoo Court

  • Drainage, road preparation, kerbing, asphalt July - August 2019

Deliveries to Site

  • Late April 2019 – October 2019

Final works

  • Barriers, new fencing and gates, street lighting, signage and linemarking September 2019
  • Landscaping and verge reinstatement October/November 2019

Completion

  • November 2019