Share Jandakot Road - March to November 2019 on FacebookShare Jandakot Road - March to November 2019 on TwitterShare Jandakot Road - March to November 2019 on LinkedinEmail Jandakot Road - March to November 2019 link
Consultation has concluded
Georgiou Group has been appointed to deliver the upgrade of Solomon Road and Jandakot Road in Treeby, from 5 March to November 2019.
Timeframes are subject to change and depend on weather conditions. Electronic signboards will advise key information. On various nights, traffic management with lane closures will be in place while contractors relocate signs, install barriers and line marking, and remove the existing road medians.
Please drive carefully and adhere to the speed limit and directional signs. Nearby residents may experience construction-related noise and vibration. Every effort will be made to minimise disruption to the local community. Thank you for your patience while we complete these vital works. If you have any questions, please contact Georgiou Project Manager Toby Taylor on 0437 805 163.
In related news, the final drawings for the next stage of Jandakot Road upgrade, due to be delivered in 2020 are shown here. A copy of drawings can be reviewed on request at the Admin Centre in Spearwood on request. Please email [email protected].
Milestones
Preliminary work includes:
Relocate existing fencing late March 2019
Clearing, topsoil, cut to fill, cut to spoil, late March
Install Water Corporation main water bore April 2019
Relocate gas main April 2019
Drainage works May 2019
Western Power relocation works April - July 2019
Dollier Street
Drainage and roadworks April - May 2019
East ofSolomon Road:
Road preparation and kerbing May - June 2019
Footpaths May 2019
Asphalt June 2019
West of Solomon Road:
Asphalt July 2019
Road preparation and kerbing July 2019
Pepperworth Place
Draining and roadworks July 2019
Solomon Road
Reinstatement of pavement July - August 2019
Install new fencing and gates July 2019
Solomon Road Southworks September 2019
Jandakot Road
Remove existing fencing late March 2019
Excavate trenches and install underground cables (Western Power) April - May 2019
South of Jandakot Road:
Clearing, drainage works and March - April 2019
Road base preparation and kerbing May - June 2019
Footpaths and asphalt July 2019
Reinstatement of existingJandakot Road
Drainage works April 2019
Construct temporary pavement May 2019
Seal road July 2019
Footpaths July 2019
Asphalt July 2019
Tie in point works to existing Jandakot Road west side
Drainage
Road preparation and kerbing
Asphalt
Tie in point works to existing Jandakot Road east side
Drainage, road preparation and kerbing September 2019
Fraser Road
Earthworks, Drainage, Roadworks April - May 2019
Cessna Drive
Drainage, road preparation, kerbing asphalt July - August 2019
Coonadoo Court
Drainage, road preparation, kerbing, asphalt July - August 2019
Deliveries to Site
Late April 2019 – October 2019
Final works
Barriers, new fencing and gates, street lighting, signage and linemarking September 2019
Landscaping and verge reinstatement October/November 2019
Completion
November 2019
Georgiou Group has been appointed to deliver the upgrade of Solomon Road and Jandakot Road in Treeby, from 5 March to November 2019.
Timeframes are subject to change and depend on weather conditions. Electronic signboards will advise key information. On various nights, traffic management with lane closures will be in place while contractors relocate signs, install barriers and line marking, and remove the existing road medians.
Please drive carefully and adhere to the speed limit and directional signs. Nearby residents may experience construction-related noise and vibration. Every effort will be made to minimise disruption to the local community. Thank you for your patience while we complete these vital works. If you have any questions, please contact Georgiou Project Manager Toby Taylor on 0437 805 163.
In related news, the final drawings for the next stage of Jandakot Road upgrade, due to be delivered in 2020 are shown here. A copy of drawings can be reviewed on request at the Admin Centre in Spearwood on request. Please email [email protected].
Milestones
Preliminary work includes:
Relocate existing fencing late March 2019
Clearing, topsoil, cut to fill, cut to spoil, late March
Install Water Corporation main water bore April 2019
Relocate gas main April 2019
Drainage works May 2019
Western Power relocation works April - July 2019
Dollier Street
Drainage and roadworks April - May 2019
East ofSolomon Road:
Road preparation and kerbing May - June 2019
Footpaths May 2019
Asphalt June 2019
West of Solomon Road:
Asphalt July 2019
Road preparation and kerbing July 2019
Pepperworth Place
Draining and roadworks July 2019
Solomon Road
Reinstatement of pavement July - August 2019
Install new fencing and gates July 2019
Solomon Road Southworks September 2019
Jandakot Road
Remove existing fencing late March 2019
Excavate trenches and install underground cables (Western Power) April - May 2019
South of Jandakot Road:
Clearing, drainage works and March - April 2019
Road base preparation and kerbing May - June 2019
Footpaths and asphalt July 2019
Reinstatement of existingJandakot Road
Drainage works April 2019
Construct temporary pavement May 2019
Seal road July 2019
Footpaths July 2019
Asphalt July 2019
Tie in point works to existing Jandakot Road west side
Drainage
Road preparation and kerbing
Asphalt
Tie in point works to existing Jandakot Road east side
Drainage, road preparation and kerbing September 2019
Fraser Road
Earthworks, Drainage, Roadworks April - May 2019
Cessna Drive
Drainage, road preparation, kerbing asphalt July - August 2019
Coonadoo Court
Drainage, road preparation, kerbing, asphalt July - August 2019
Deliveries to Site
Late April 2019 – October 2019
Final works
Barriers, new fencing and gates, street lighting, signage and linemarking September 2019
Landscaping and verge reinstatement October/November 2019