Following community consultation in early 2022, the City has been working with architects to finalise designs for the new anti-climb structures for the Othello and Maraboo bridges.
Design outcomes
In line with community preferences, architects opted for an open-structure design (Design A) and perforated panels with marine-themed shapes. Additional design feedback has been considered where viable from an engineering, maintenance and budget perspective.
Next steps
Consultation has concluded.
The City expects to go out to tender for construction in early 2023. The City anticipates the anti-climb structures to be installed by late 2023; however, due to the current global economic conditions, timing is subject to material availability and budget.
More information
For more information please contact the project team on 08 9411 3444 or [email protected].
Share Project Update: May 2022 on Facebook
Share Project Update: May 2022 on Linkedin
Email Project Update: May 2022 link
Thank you for your feedback
The City asked for your feedback on two design options for new anti-climb structures on the Othello and Maraboo bridges in North Coogee. We also asked which artwork themes we should consider for some perforated panels, which will form part of these structures.
What we heard
Project communications were sent to over 500 North Coogee residents and signs were installed on site. More than 350 people visited the project page and 88 people provided feedback. Thank you for having your say.
- Design A (open design anti-climb structure) is the preferred design (78.5% prefer Design A; 4.5% prefer Design B; 2.5% prefer both; and 14.5% prefer none of the options).
-
Why respondents prefer Design A:
- Aesthetics,
- Perceived cost,
- Design (most difficult to climb),
- Lower maintenance, and
- Safety (open design appears safer to walk through in periods of low light).
- ‘Marine’ is the preferred (73%) artwork theme for the perforated panels.
-
Why respondents prefer ‘marine’ theme:
Next steps
Key findings have been reviewed will be considered in the final design process. When available, a final project update will be detailed on this page. The upgrades are expected to be installed in the 2022-23 financial year.
More information
For more information about this project please contact the project team on 08 9411 3444 or [email protected].